Clear Creek Apartments
![Clear Creek Apartments](https://uploads-ssl.webflow.com/63000131d9a25df1d5a8c14e/63000131d9a25d4786a8c153_1.jpg)
Project
Clear Creek Apartments
Owner
Consolidated Investment LLC
EMC Role
Subcontractor
Engineer
Woodson Engineering
Project Overview
EMC moved 100,000 CY of rock / dirt within 3 months, utilizing a crushing operation with a XXX Crusher and a D-11 Dozer. EMC quickly moved into pad development, delivering the building sites ahead of schedule. Additional scopes include:
- 30,000 LF of underground pipe laid
- 45,000 SF of concrete sidewalk
- 18,000 LF of curb and gutter
- 30,000 SY of asphalt