Beulah & University CMAR

Project
Beulah & University CMAR
Owner
EMC Role
Engineer
Project Overview
This project extended the old Beulah Boulevard northward to the old University Avenue, with a roundabout constructed at the new intersection. It included ~100,000 cy’s of earthwork for the main roadway; ~75,000 sf of sidewalk & FUTS multi-use path; a 120’ long x 25’ wide Contech pre-cast arch, pedestrian underpass under Milton Rd.; ~3,500 lf new waterline; 1,400 lf of new sewer main; and ~3,300 lf of new storm mains.