Eagle Mountain Construction Projects

Municipal & Private Utilities
Leroux St Improvements Project - CMAR - Flagstaff, AZ - $2,081,415.67

Owner: City of Flagstaff

EMC Role: CMAR

Contract Value: $2,119,350.00

Engineer: WLB Engineering

Start Date: October 2015

Completion Date: May 2016

Project Description: This project consisted of replacing the existing water main through the heart of downtown Flagstaff. The project included over 3,300 LF of 8" waterline, replacement of over 40 water services and 20 sewer services. EMC also constructed 2,700 LF of curb and gutter, over 5,600 SF of sidewalk and over 10,000 SY of AC paving. This project included many challenges, such as site congestion, working with local businesses and residents to keep access and its proximity to downtown as well as half of the new waterline needed to go through rock. EMC utilized different methods to work around some of these obstructions such as:

  • EMC worked with the design engineer and raised a section of the new water main to avoid some of the hard rock, which in turn expedited the schedule saving 1 - 2 weeks.
  • Water ties ins were schedule during specific time frames in the early hours of morning to accommodate different stakeholders needs such as the bars, restaurants and hotels to make sure it did not negatively effect their business.
  • Extra water valves were added to limit the amount of water shutdown time, ensuring we were able to hit the required downtime on the businesses.
  • EMC worked with the City and design engineer to move valves of add valves in order to keep residents online during testing of the new water main, allowing for very minimal disruption at tie over.
  • Installing a temporary, above ground, water services was utilized in a instance were a fire line per the plan was actually a service. This temporary service allowed for EMC to completed the new line while keeping the bars, restaurants and offices functioning as usual.
  • All trenches were backfilled or plated after work hours to ensure the safety of the general public.

Several existing utility lines had to be relocated, EMC coordinated relocations with each Utility Franchises to align with our master schedule, minimizing overall impact.

EMC, with a complicated project in a congested part of town, was able to bring this project 4.5 months ahead of schedule. An un-contracted promise to the downtown business alliance of completing the downtown area prior to Memorial Day weekend was delivered 3 weeks ahead of schedule. This was accomplished by being able to work through the winter months, and being a local contractor allowed us the ability to remobilize as soon as acceptable weather presented itself. Along with being ahead of schedule EMC was able to deliver this project under budget, proving that our GMP pricing structure was accurate.

Click images to view larger

Leroux Street Improvements - Flagstaff, AZ
Leroux Street Improvements - Flagstaff, AZ
Leroux Street Improvements - Flagstaff, AZ
Leroux Street Improvements - Flagstaff, AZ
12th Street Improvement Project - Cottonwood, AZ - $1,290,299.44

Owner: City of Cottonwood

EMC Role: Prime Contractor

Contract Value: $1,290,299.44

Engineer: Pender Engineering

Start Date: March 2015

Completion Date: October 2015

Project Description: Demo existing road, 20,000 CY of new Earthwork including cut/fill, 900 LF of New storm drain w/ headwalls and rip rap, plunge pools. 3400 LF of New reclaim and potable water lines, APS utilities. 3500 LF of New curb/gutter, 20,000 SF of new sidewalks and parkway grading landscaping w/ Keystone retaining walls, 5900 SY of new Asphalt Paving, striping and signage.

Several existing utility lines had to be relocated, EMC coordinated relocations with each Utility Franchises. EMC completed the project on time and under budget.

Click images to view larger

12th Street Improvement Project - Cottonwood, AZ
12th Street Improvement Project - Cottonwood, AZ
12th Street Improvement Project - Cottonwood, AZ
12th Street Improvement Project - Cottonwood, AZ
12th Street Improvement Project - Cottonwood, AZ
12th Street Improvement Project - Cottonwood, AZ
Industrial Dr. Improvement Project - Flagstaff, AZ - $1,495,318.26

Owner: City of Flagstaff

EMC Role: Prime Contractor

Contract Value: $1,495,318.26

Engineer: Turner Engineering

Start Date: April 2015

Completion Date: November 2015

Project Description: This project consisted of improving an existing dirt road while adding a new waterline and many drainage improvements. Too establish the new roadway grades over 12,000 CY of material was moved. EMC installed over 2000 ft of 12” water main, 700 ft of 8” sanitary sewer, manholes, and 1300 LF of larger diameter ductile iron Storm drain. EMC installed, as part of the overall storm drain system (2) underground LID storage chambers to collect and filter the storm run off. 2 cast in place retaining walls were also constructed to accommodate the new road alignment with an existing bridge abutment as well as the track beds for BNSF railway. Surface improvements included 4300 LF of new curb, 5000SF of new sidewalk as well as over 9600 SY of new Asphalt Pavement.

Several existing utility lines had to be relocated, EMC coordinated relocations with each Utility Franchises. EMC completed the project on time and under budget.

Click images to view larger

Industrial Dr. Improvement Project - Flagstaff, AZ
Industrial Dr. Improvement Project - Flagstaff, AZ
Industrial Dr. Improvement Project - Flagstaff, AZ
Industrial Dr. Improvement Project - Flagstaff, AZ
Franklin & Mohawk Street Improvements - Flagstaff, AZ - $1,229,100

Owner: City of Flagstaff

EMC Role: Prime Contractor

Contract Value: $1,229,100

Engineer: WLB Group

Start Date: October 2011

Completion Date: May 2012

Project Description: This project was completed by EMC for the City of Flagstaff under the 2010 bond project from 8/15/11 to 1/31/12. The project consisted of the installation of over 2,200 LF of 12” C-900 waterline, 1,050 LF of 8” DIP waterline, 350 LF of 8” DIP sewer, 20 new water meter/service connections, 6 fire hydrants, and 11 sewer service connections. Incidental to the utility construction was the removal and replacement of over 7315 square yards of asphalt, installation of 2,645 LF of curb and gutter, and the removal and replacement of 7,190 SF of new sidewalk including all required ADA compliant ramps and driveways. This Project was allowed a winter shutdown, due to paving occurring in the winter, and EMC was still able to complete the Project 1 month ahead of schedule, and within the COF budget.

Click images to view larger

Franklin & Mohawk Street Improvements - Flagstaff, AZ
Franklin & Mohawk Street Improvements - Flagstaff, AZ
Franklin & Mohawk Street Improvements - Flagstaff, AZ
Franklin & Mohawk Street Improvements - Flagstaff, AZ
Franklin & Mohawk Street Improvements - Flagstaff, AZ
Cherry Ave. Drainage Project - Flagstaff, AZ - $506,975

Owner: City of Flagstaff

EMC Role: Prime Contractor

Contract Value: $506,975

Engineer: WLB Group

Start Date: March 2011

Completion Date: October 2011

Project Description: This project was completed by EMC for the City of Flagstaff from 4/4/11 to 8/22/11. This project included the removal and replacement of over 780 LF of 8” sewer along with 21 sewer service connections & cleanouts. Water services to five existing residences were also removed and replaced. EMC removed 6 manholes and installed 2 new manholes. Storm drain construction included over 1,200 LF of 30” to 42” drainage pipe, associated headwalls and catch basins. Incidental to the utility construction was the removal and replacement of over 1,400 SY of asphalt, 230 LF of curb and gutter, 1,255 SF of new sidewalk including all required ADA compliant ramps and driveways. This Project did not require a winter shutdown, and the Project completed on time, and within the COF budget.

Click images to view larger

Cherry Ave. Drainage Project - Flagstaff, AZ
Cherry Ave. Drainage Project - Flagstaff, AZ
Cherry Ave. Drainage Project - Flagstaff, AZ
Renaissance Phase II Street Improvements - Winslow, AZ – $1.9 million

Owner: City of Winslow

EMC Role: General Contractor

General Contractor: EMC

Contract Value: $1,950,000

Engineer: David Evans & Associates

Start Date: November 2009

Completion Date: August 2010

Project Description: The City of Winslow revamped their downtown streets with utility reconstruction and streetscape enhancements (e.g. new curb, gutter, sidewalk, landscaping and street furniture) on Historic US route 66. The Project required extensive phasing and traffic control to keep the downtown merchants in business, and their clients with safe and easy access. The Project consisted of:

  • 5,200 LF of curb and gutter
  • 22,000 SF of sidewalk & pavers
  • New street lights
  • Route 66 monument
  • New landscaping

Click images to view larger

Arizona Sidewalk and Landscape Contractor
Arizona Streetscape Enhancement Contractor
Arizona Curb Gutter Sidewalk Development
Renaissance Phase II Street Improvements - Winslow, AZ
Site Development
Northern Arizona University Science and Health Building – Northern Arizona University - Flagstaff, AZ - $2,083,393.80

Owner: Northern Arizona University

EMC Role: Subcontractor

General Contractor: M.A Mortenson Construction

Engineer: GLHN

Contract Value: $2,083,393.80

Start Date: June 2013

Completion Date: November 2015

Project Description: The Northern Arizona Science and Health Building was a ground up new construction structure which included classrooms, lecture halls and specialty laboratories. EMC performed as a subcontractor for M.A Mortenson Construction. This project had many inherent restrictions mainly due to the lack of room at the site. The work EMC performed included general over-excavation and basement excavation which was all completed as other trades started the building. EMC was able to coordinate our efforts to balance the need of production but also accommodate these subs as well as the overall project. Also included with EMC scope of work were utilities such as domestic and reclaimed water, sewer as well as chilled water systems.  EMC dug and installed a 10’X10 precast tunnel system which included 3 vaults with sump discharge systems. This projects storm drain system was a series of underground detention tanks. EMC installed the (2) 70’ X12’ diameter tanks and completed he discharge system with a series of pumps and controls. EMC finished up the project by completing the site paving as well as improvements to the adjacent pedway.

Click images to view larger

Northern Arizona University Science and Health Building
Northern Arizona University Science and Health Building
Northern Arizona University Science and Health Building
Northern Arizona University Science and Health Building
Navajo Nation Justice Center - Tuba City, AZ - $4,016,307

Owner: Navajo Nation Justice Center

EMC Role: Subcontractor

General Contractor: Arviso Okland Construction

Contract Value: $4,016,307

Start Date: October 2011

Completion Date: November 2012

Project Description: This project consists of complete site development, including:

  • 200,000 CY’s of mass earthwork
  • 6,000 LF of water & fire service
  • 2,000 LF of 8” sewer
  • 2,800 LF of 12-24” storm drain CMP & HDPE
  • 22,000 SY’s of pavement
  • 9,800 LF of curb & gutter

Click images to view larger

Navajo Nation Justice Center - Tuba City, AZ
Navajo Nation Justice Center - Tuba City, AZ
Navajo Nation Justice Center - Tuba City, AZ
Navajo Nation Justice Center - Tuba City, AZ
Navajo Nation Justice Center - Tuba City, AZ
Elevation Apartments - Flagstaff, AZ - $2,567,060

Owner: Vendura Residential

EMC Role: Subcontractor

General Contractor: Wespac Construction

Contract Value: $2,567,060

Start Date: November 2011

Completion Date: July 2012

Project Description: EMC performed all the site work including over ex of building pads and grading for the entire 14 acre site, totaling 44,000 CY. EMC also installed all the onsite and offsite utilities which included:

  • 6,500 LF of 8” water mainline
  • 5,600 LF of 8” sewer line
  • 8,950 LF of storm drain ranging from 4” to 45”
  • 11,700 LF of Curb & Gutter, 7,700 SF of VG, and 23,400 SY of Asphalt

One of the challenges to this project is that the site was divided into 3 Phases of construction. Once one phase of dirt work was completed other subs were allowed to start their scope which involved a lot of coordination and congestion in small work areas. Construction also involved working through two winter seasons with weather impacts. Another issue was EMC having to re work our scope due to damage from other subs. Conflicts with existing utilities not identified correctly on the construction plans.

Click images to view larger

Elevation Apartments - Flagstaff, AZ
Elevation Apartments - Flagstaff, AZ
Elevation Apartments - Flagstaff, AZ
The Grove at Flagstaff - Flagstaff, AZ - $1,757,139

Owner: Campus Crest Development

EMC Role: Subcontractor

General Contractor: Campus Crest

Contract Value: $1,757,139

Start Date: November 2011

Completion Date: August 2012

Project Description: EMC was contracted for all the site work including over Ex building pads and grade for new parking lots. For a total of 8000 CY of dirt. Install all the water and sewer mainline and services which included 1100’ LF of water and 500’LF of Sewer, tying into existing utilities in existing paved streets while keeping access to traffic.

We also installed 7,000 LF of Curb & Gutter, 27,050 SF of sidewalk and 15,722 SF of Asphalt. Challenges included starting and working through winter and coordinating site access with multiple other subs. The owner had deadlines for occupancy for college students prior to start of the next semester of school. EMC worked overtime man hours to accommodate this schedule with several delays due to other subs. But overall the contractor was happy for our effort in meeting this schedule. Due to the fact that EMC was a local contractor the general relied on us heavily to do more scope that was originally contracted

Click images to view larger

The Grove at Flagstaff - Flagstaff, AZ
The Grove at Flagstaff - Flagstaff, AZ
The Grove at Flagstaff - Flagstaff, AZ
Clear Creek Apartments Site Development - Flagstaff, AZ - $5.1 million

Owner: Consolidated Investment LLC

EMC Role: Subcontractor

General Contractor: Wespac Construction

Contract Value: $5,160,000

Engineer: Woodson Engineering

Start Date: August 2009

Completion Date: April 2011

Project Description: EMC moved 100,000 CY of rock / dirt within 3 months, utilizing a crushing operation with a XXX Crusher and a D-11 Dozer. EMC quickly moved into pad development, delivering the building sites ahead of schedule. Additional scopes include:

  • 30,000 LF of underground pipe laid
  • 45,000 SF of concrete sidewalk
  • 18,000 LF of curb and gutter
  • 30,000 SY of asphalt

Click images to view larger

Flagstaff Arizona Pad Development
Rock Curshing Flagstaff Arizona
Flagstaff Arizona Site Development
Clear Creek Apartments Flagstaff Arizona
Marriot Hotel Site Development - Flagstaff, AZ - $3.4 million

Owner: The Summit Group

EMC Role: Prime Contractor on the Civil

General Contractor: Wespac Construction

Contract Value: $3,490,000

Start Date: August 2008

Completion Date: May 2009

Project Description: Site development for the Marriot Hotel. The limestone soil conditions and the proximity to I-17 and I-40 required the site be profiled to accomplish the nearly 60,000 CY of excavation. Much of the resulting material was used for backfill and site fill areas. The Project consisted of:

  • 60,000 CY of cut / fill
  • Site Utilities
  • Site Concrete
  • 80,000 SF of asphalt

Click images to view larger

Arizona Underground Utility Contractor
Arizona Backfill
Arizona Hotel Site Development
Marriot Hotel Site Development - Flagstaff, AZ
Drainage
Pan Dam Decommissioning - Seligman, AZ - $623,705

Owner: BNSF Railway

EMC Role: General Contractor

Contract Value: $623,705

Engineer: Tetra Tech

Start Date: April 2012

Completion Date: October 2012

Project Description: This project consisted of decommissioning the Pan Dam which was originally built in the 1800’s. The first part of the decommissioning was to remove and place the sediment that had filled in the dam over the years. EMC moved a total of 20,000 CY of sediment and placed it back on the existing slopes. The next phase was removed the center portion of the existing dam creating an avenue for water to pass through the dam. The final part of the decommissioning involved permanent sediment and stormwater measures which included: multiple check dams, 70 CY of concrete slabs, 175 CY of grouted rip rap, 80 SY of shotcrete, 500 CY of gabion mattresses, 5300 SY of geo-textile fabric and 8 acres of site revegetation.

The remoteness of this project, site access and some large weather events during construction were some of the obstacles EMC faced, but overcame to meet our schedule. EMC’s scheduling and planning was a key factor in dealing and managing these challenges.

Click images to view larger

Pan Dam Decommissioning - Seligman, AZ
Pan Dam Decommissioning - Seligman, AZ
Pan Dam Decommissioning - Seligman, AZ
Pan Dam Decommissioning - Seligman, AZ
Pan Dam Decommissioning - Seligman, AZ
Pan Dam Decommissioning - Seligman, AZ
Finne Flat Channel - Camp Verde, AZ - $1,048,104

Owner: Town of Camp Verde, AZ

EMC Role: Prime Contractor

Contract Value: $1,048,104

Engineer: GHD Engineering

Start Date: March 2012

Completion Date: October 2012

Project Description: This project consisted of:

  • 3,000 LF of realignment and construction of a concrete channel
  • 200 LF of box culvert across Finne Flat Highway
  • Relocation of electrical, storm drain, and sewer conflicts

Click images to view larger

Finne Flat Channel - Camp Verde, AZ
Finne Flat Channel - Camp Verde, AZ
Finne Flat Channel - Camp Verde, AZ
Finne Flat Channel - Camp Verde, AZ
Campbell Avenue Drainage - Flagstaff, AZ - $971,029

Owner: Coconino County Public Works

EMC Role: General Contractor

Contract Value: $971,029

Engineer: Turner Engineering, Inc.

Start Date: May 2011

Completion Date: October 2011

Project Description: The Project consisted of:

  • Installed 27,000 SF of reinforced concrete floor with 12,000 LF of Gabion Baskets
  • Site Utilities - Several existing utility lines had to be coordinated for relocation, which we scheduled and performed in conjunction with each utility company
  • 80,000 SF of asphalt

Click images to view larger

Campbell Avenue Drainage - Flagstaff, AZ
Campbell Avenue Drainage - Flagstaff, AZ
Campbell Avenue Drainage - Flagstaff, AZ
Campbell Avenue Drainage - Flagstaff, AZ
Miscellaneous
Navajo Dept. of Youth Utilities & Ball Fields – Ft. Defiance, AZ - $967,000

Coming Soon!

Hopi Housing Facility Waterline - Pollaca, AZ - $300,000

Coming Soon!

Eunice WTF Pond Construction - Eunice, NM - $578,000

Coming Soon!

Clear Creek Offsite Sewer Extension - Flagstaff, AZ - $589,000

Coming Soon!

Pulliam Airport Drainage - Flagstaff, AZ - $988,000

Coming Soon!

Winslow Water Line Replacement - Winslow, AZ - $703,000

Coming Soon!

Flagstaff Mall Underground Utilities - Flagstaff, AZ - $7.8 million

Coming Soon!

J.W. Powell Blvd. - Flagstaff, AZ - $1.2 million

Coming Soon!